Project Plan
Tate Marske
May 13th,
2012
Email Notifier
1.
Project
Overview:
The Email Notifier is a project which is set to be
completed in a total of eight weeks. For
the purposes of this document, the timeframe for completed aspects of this
project have been split into increments of 1 week. This document will provide guidelines as to
how the project shall progress to become a complete, prototyped product within
these eight weeks of development.
2.
Project
Development Management
2.1
Organization and Resources
By
structuring the project so that each week will have a clear-cut and reachable
goal in the development process, I have eliminated the need for back-tracking
or reconfiguration of product implementations and assets. Each week, I will be completing a major
portion of the project based on sturdy and reasonable milestones.
2.2
Personnel
In
the case of this project, I am the only person who will be working on the Email
Notifier. Therefore, I will be
responsible for all of the physical assembly of the product as well as the
programming required to serve as the framework for this product. Thankfully, I am following a general tutorial
to help me set this project up and implement the code.
3.
Schedule
and Milestones
Week 1:
Internal Hardware must be acquired.
START – W1 END
– W1
Week 2:
Internal Hardware studied, and programming language mostly understood.
START – W1 END
– W2
Week 3: Framework
code completed.
START – W2 END
– W3
Week 4: PHP
code completed and running on local server.
START – W3 END
– W4
Week 5: Enclosure
and external hardware acquired.
START – W4 END
– W5
Week 6: Enclosure
functional and all code working properly.
START – W5 END
– W6
Week 7: Bug
tested and fully functioning code and hardware.
START – W6 END
– W7
Week 8: Full
product ready to present and all bugs worked out.
START – W7 END
– W8